PULLMAN removed and replaced the original ventilating window for the Unit 1 turbine as part of a capital improvement of the historic powerhouse that is still an active hydroelectric facility while maintaining its original historic features.

Project Overview

  • Historic facility constructed in 1911
  • Largest hydroelectric plant along the Mississippi River

Originally constructed in 1911, the Ameren Keokuk Hydropower Plant is listed on the National Register of Historic Places and is the largest hydroelectric plant along the Mississippi River. Blending more than a century of history with modern power generation, the facility presents a unique challenge of preserving its historic features while maintaining the operations of an active power plant.

Constructed before the invention of modern HVAC controls, the plant uses large windows to act as operating sashes that regulate the air temperature around the power generating turbines.  The original sashes are still in use today but needed replacement. PULLMAN leveraged an ongoing relationship with the Owner, to remove and replace one of the existing ventilating windows in order to better understand the construction process that would be needed to later upgrade the remaining original windows. 

Construction required careful planning to address restoration of the building façade around the window opening, accommodating ongoing power generation operations, and challenging access conditions.  The replacement window was designed to look identical to the original while retaining its existing mechanical system used to regulate the turbines. This preserved the original operating interface, which has remained unchanged since the plant’s construction. This project highlights PULLMAN’s expertise in preserving historic infrastructure at a large scale while keeping strict safety and quality standards

PROJECT INFO

  • Location: Keokuk, IA
  • Specialty Contractor: PULLMAN