Saint Vincent Hospital | LINAC Upgrade
Saint Vincent Hospital | LINAC Upgrade | Worcester, MA
At Saint Vincent Cancer & Wellness Center, DPR renovated an existing concrete vault to support the installation of a new Varian linear accelerator (LINAC). The project included new MEP infrastructure within the treatment space and chilled water piping routed to new mechanical equipment installed on the roof.
Partners
-
Client Saint Vincent Hospital
Early Coordination for Precise Execution
DPR’s in-house VDC team brought certainty to a highly constrained installation by coordinating critical details before work reached the field. With limited space inside the existing vault and tight equipment tolerances, DPR laser scanned existing conditions and incorporated them into BIM coordination to validate MEP routing, identify spatial constraints and resolve conflicts early.
That planning carried directly into construction. DPR worked closely with Varian and the broader project team to align equipment requirements with the design and construction documents while coordinating multiple installation vendors. DPR’s self-perform team executed demolition, concrete, drywall and ACT scopes, providing greater control over critical field activities and strengthening the connection between coordination and execution. Together, these efforts helped the team address unexpected conditions in the field while maintaining the precision required for installation.
DPR's coordination for the Varian TrueBeam with VisionRT installation at Saint Vincent Hospital was exceptional, seamlessly managing multiple vendors with a can-do attitude to ensure a flawless install. Their proactive planning and ability to easily solve multiple unexpected challenges kept the project on schedule, meeting all technical and timeline requirements with precision.
John Rossman, Medical Physicist
Saint Vincent Cancer & Wellness Center
Building Around an Active Cancer Center
Working within an active cancer center required DPR to plan well beyond the immediate limits of the LINAC vault. The team worked closely with hospital end users and department leads to sequence activities around ongoing operations while the adjacent LINAC vault remained active. That same level of planning extended outside the building, where the team navigated extensive permitting requirements with the local AHJ and coordinated two crane picks in downtown Worcester. Flaggers and police details supported traffic flow during the picks, helping minimize impacts to hospital operations and the surrounding site.
Expanding Access to Advanced Treatment
To celebrate the project’s successful delivery and the collaboration that made it possible, DPR joined the hospital team for a ribbon cutting ceremony marking the opening of the new space. The completed renovation provides Saint Vincent Cancer & Wellness Center with an updated treatment environment that supports the hospital’s continued delivery of cancer care to the Greater Worcester community.