Vibrant Office Relocation for Freddie Mac
Freddie Mac Regional Office Relocation | Plano, TX
This project includes a 155,000-sq.-ft., second-generation finish-out for Freddie Mac's new Dallas Headquarters in an occupied facility. The finish-out was completed in two phases for phased occupancy. The new headquarters includes six IDF rooms, one MDF room, eight electrical rooms, two AV closets and 640 poke-throughs. There are also two 750kva redundant generators with associated UPSs with external, internal and static ATS switches. Architecturally, there are four market areas, two working zones, multiple conference rooms, executive offices and high-end custom finishes, as well as custom acoustical treatments.
Accelerating Schedule through Self-Perform Work
The DPR team heavily collaborated with and utilized its self-perform work (SPW) teams on many facets of work on this project. Because the team utilized all of these SPW trades, the DPR team was able to shave one month off of the final schedule while increasing overall project quality and safety.
Overcoming Challenges with Innovative Solutions
Supply Chain Shortage
At the start of preconstruction, the market was facing material shortages that would affect the design assist process with the owner, the design team and early MEP trade partners, and ultimately impact the project. The first concern, and a critical path item, was the metal studs. The cold-formed 20-foot metal studs were currently experiencing a 20-week lead time due to supply chain constraints. The original schedule assumed 10-weeks.
Prefabricating In-House
Our team identified this schedule risk quickly and worked together to come up with a plan to creatively address the delay. The team decided to call upon our in-house prefabrication team and utilize an innovative technique to print the metal studs instead. The entire printing process took a total of 10 days and the teams’ solution allowed for the project to continue 8 weeks ahead of schedule.
Innovative Solutions
Supply Chain Shortage
At the start of preconstruction, the market was facing material shortages that would affect the design assist process with the owner, the design team and early MEP trade partners, and ultimately impact the project. The first concern, and a critical path item, was the metal studs. The cold-formed 20-foot metal studs were currently experiencing a 20-week lead time due to supply chain constraints. The original schedule assumed 10-weeks.
Prefabricating In-House
Our team identified this schedule risk quickly and worked together to come up with a plan to creatively address the delay. The team decided to call upon our in-house prefabrication team and utilize an innovative technique to print the metal studs instead. The entire printing process took a total of 10 days and the teams’ solution allowed for the project to continue 8 weeks ahead of schedule.
Our employees and executives love the space and are thrilled to work in this beautifully designed and constructed workplace. [We have] received multiple compliments on the office which we pass along to you all! Continued gratitude to you for your partnership throughout this entire project.
Linda Bock
Freddie Mac Project Manager