Scaling a Network Facility in Dallas-Fort Worth
Confidential Client | Data Center Campus | Southlake, TX
Since 2020, DPR has finished a series of projects at this live network facility totaling over $300 million. Together they cover the site's test labs, battery and UPS power, cooling and backup generators. Much of the work happened at the same time: in 2023 the team had up to seven jobs running at once, including the lab air handlers, generators 1 and 6 and the chiller yard. All of it was done in an occupied, mission-critical building under the customer's change freezes and MOPs.
Network Test Lab & AHUs
DPR completed a full gut and rebuild of the customer's network test lab, where outages are recreated to test network recovery. The scope included new HVAC, wiring, cable tray, fire alarm, static-dissipative flooring, hot- and cold-aisle containment and a split AC/DC power layout. A new 48-volt battery plant was also installed, along with strut, ladder rack, spill containment and Division 7 firestopping, self-performed by DPR.
To support the lab’s air-cooled servers, DPR replaced four air handlers connected to a common chilled-water loop and duct system, with two units operating and two providing redundancy. The air handlers were brought into the building in sections and assembled in place.
NEC2A Battery Upgrade
DPR originally installed lithium-ion batteries in these rooms in 2020. Due to regulation changes and customer requirements, DPR replaced with valve-regulated lead-acid (VRLA) batteries, which are replaced every five years.
Chiller Yard Remediation
DPR replaced four 500-ton chillers with five 400-ton units, maintaining the same overall capacity while improving parts availability and adding redundancy. An airflow study addressed overheating issues by informing a roughly 40-foot yard extension, rotating the chillers 90 degrees and setting them at varying heights.
The team also participated in factory witness testing in Monterrey, Mexico, where the chillers were tested at full load in a 140°F chamber alongside the commissioning agent and mechanical contractor. Each chiller was then delivered as a single unit and set by crane over several days.
Generator Tank Upgrades
DPR is replacing fuel tanks beneath the existing generators and refurbishing the generators to extend their service life. The new raised tanks meet current Steel Tank Institute standards and address corrosion caused by trapped water. Because the new configuration increased the generator height by approximately four inches, DPR added a new junction box and conduit runs to the output gear while temporary generators maintained backup power during construction.
Commissioning includes an eight-hour, 100% load-bank test followed by a simulated power failure to verify all connections. The team has also navigated long equipment lead times, discontinued generator components, and the customer's preferred-vendor requirements, while completing field-built access stairs to support the new installation.