Adding Imaging Capacity for the West Valley

Abrazo West CT Replacement | Goodyear, AZ

As only one of two Level 1 trauma centers serving the West Valley, the Abrazo West Campus continues to expand capacity to meet the needs of the communities it serves. The hospital entrusted DPR with upgrading and expanding a CT room and related infrastructure, including a shared control room serving both CTs, and reading room and IDF room. DPR coordinated closely with hospital staff to limit downtime, while maintaining schedule and quality control afforded by DPR’s self-perform work crews.

About the Project

A significant shutdown was required to install the new 600 amp circuit, affecting normal and emergency power, including the MRI. Coordination with hospital staff was crucial, especially with the radiology department, to keep one CT operational. The project involved pouring a thickened slab for structural support and extensive coordination with trades and hospital staff, concluding successfully with hospital satisfaction.

Challenges and Solutions

Eliminating Disruptions with a

High-Performing Team

As with many other enhancement projects on operating facilities, one of DPR's first goals was to align with the "Rules of the Road" of the client's onsite Operations team. This ensured our workforce maintained safety and operations protocols and caused the least disruption possible. Communicating in biweekly meetings on progress and coordinating adjustments with all stakeholders, DPR earned the client's trust and created a safer and more efficient project.

Estimating Constructability through

Early Design Involvement

DPR team members were engaged early in design to purchase long-lead equipment, give constructability input and help with schedule and budget development. Construction was out in front of the design in several areas. There were three iterations of design development, which required budget and schedule revisions, and resequencing work along with new permitting. These occurred while the base project was moving forward. Through detailed scheduled workshops, DPR was able to minimize delays.

Control room overlooking CT scanning room
View of a medical equipment room
Challenges and

Solutions

Control room overlooking CT scanning room
Eliminating Disruptions with a

High-Performing Team

As with many other enhancement projects on operating facilities, one of DPR's first goals was to align with the "Rules of the Road" of the client's onsite Operations team. This ensured our workforce maintained safety and operations protocols and caused the least disruption possible. Communicating in biweekly meetings on progress and coordinating adjustments with all stakeholders, DPR earned the client's trust and created a safer and more efficient project.

View of a medical equipment room
Estimating Constructability through

Early Design Involvement

DPR team members were engaged early in design to purchase long-lead equipment, give constructability input and help with schedule and budget development. Construction was out in front of the design in several areas. There were three iterations of design development, which required budget and schedule revisions, and resequencing work along with new permitting. These occurred while the base project was moving forward. Through detailed scheduled workshops, DPR was able to minimize delays.

Self-Perform Trades

DPR’s self-perform capabilities provided greater control over schedule, quality and coordination across key scopes. For concrete, the team managed placement from planning through execution, achieving the precise floor flatness required for the heavy CT medical equipment and reducing installation risk while supporting long-term performance.