- Status: Approved
- PTLs:
- Vish Ishaya (Nova)
- Brian Waldon (Glance)
- John Dickinson (Swift)
- Gabriel Hurley (Horizon)
- Joe Heck (Keystone)
- Dan Wendlandt (Quantum)
- John Griffith (Cinder)
- Mark McLoughlin (Oslo)
- Release Manager: Thierry Carrez (ttx)
New features must land in master branch by February 19, two days before grizzly-3 milestone delivery.
|
| Week (Thursday) |
Common | Swift |
| 2012 |
October |
18th | Design Summit |
| 25th | | |
| November |
1st | | |
| 8th | | |
| 15th | | 1.7.5 (Nov 13) |
| 22nd | grizzly-1 | |
| 29th | | |
| December |
6th | | |
| 13th | | |
| 20th | | |
| 27th | | |
| 2013 |
January |
3rd | | |
| 10th | grizzly-2 | |
| 17th | | |
| 24th | | 1.7.6 |
| 31st | | |
| February |
7th | | |
| 14th | | |
| 21st | FeatureFreeze (Feb 20) StringFreeze (Feb 20) grizzly-3 | |
| 28th | | |
| March |
7th | | |
| 14th | Release candidates |
| 21st |
| 28th |
| April |
4th | Grizzly Release (2013.1) |
| 11th | | |
| 18th | Design Summit |
|