Curtailment
Resolved Jan 15 at 02:45am EST
Norway grid is currently under heavy utilization and curtailment has been scheduled for the next few hours. An update will be provided as soon as operations are resumed.
Operations have been resumed.
Hydro container B12 in maintenance
Resolved Jan 14 at 10:05am EST
We would like to inform you that container B12 is temporarily out of service due to scheduled firmware updates and general maintenance activities.
We are pleased to inform you that the consumption levels for container B12 have been fully restored to normal.
The event began on January 14, 2026, at 07:19 (GMT -3) and concluded at 16:24 (GMT -3), with a total duration of 9 hours and 5 minutes.
The restoration of container B12 took longer than initially expected due to additional consumpt...
Container B22 in maintenance
Resolved Jan 13 at 06:45am EST
We would like to inform you that container B22 is temporarily out of service due to scheduled firmware updates and general maintenance activities.
This event began at
ANDE Utility Curtailement - reduced load
Resolved Jan 12 at 10:34am EST
The power utility, ANDE, has initiated a curtailment due to grid congestion. Estimated duration is 5 hours.
We are pleased to inform you that the consumption levels have been restored to normal.