Programme schedule

Each cycle begins with a Call for Proposals, followed by a condensed space project lifecycle, including typical design phases and reviews, culminating in the launch of the experiments and publication of the final reports.

The REXUS/BEXUS programme started in 2007 in its current form.

This diagram shows an example of overlapping cycles of the programme with the key milestones:

Click on diagram for bigger view

The detailed schedule for the current cycles of activities is as follows:

Cycle 16:

BEXUS 36/37 schedule

  • 14-16 May 2025 – BEXUS Critical Design Reviews (CDRs), ESA, ESTEC
  • Jul 2025 – BEXUS Integration Progress Reviews (IPRs) at student team sites
  • Aug/Sep 2025 – BEXUS Experiment Acceptance Reviews (EARs) at student team sites (ESA/SNSA) or ZARM-FAB Bremen (DLR)
  • 3-13 Oct 2025 – BEXUS Campaign (10 days), SSC, Esrange Space Center
  • TBD Jan 2026 – Delivery of the final BEXUS Experiments reports

REXUS 35/36 schedule

  • 4-6 Jun 2025 – REXUS Critical Design Reviews (CDRs), DLR Oberpfaffenhofen
  • Aug 2025 – REXUS Integration Progress Reviews (IPRs) at student team sites
  • Nov 2025 – REXUS Experiment Acceptance Reviews (EARs) at student team sites
  • 8-12 Dec 2025 – Integration Week (ITW), ZARM-FAB Bremen
  • 12-16 Jan 2026 – Bench Test, DLR Oberpfaffenhofen
  • 2-14 Mar 2026 – REXUS Campaign (12 days), SSC, Esrange Space Center
  • TBD Jun 2026 – Delivery of the final REXUS Experiments reports

Cycle 17:

  • 18 Jun 2025 – Call for Experiment Proposals
  • Sep 2025 – Letter of intent (DLR Only)
  • 13 Oct 2025, 23:59 CEST – Deadline for Experiment Proposals
  • 24-25 Nov 2025 – DLR Selection Workshop, DLR
  • 25-27 Nov 2025 – ESA/SNSA Selection Workshop, ESA/ESTEC
  • Dec 2025 – Cycle 17 selection announcement
  • 26-30 Jan 2026 – Preliminary Design Reviews (PDRs) & Students Training Week, SSC, Esrange Space Center

BEXUS 38/39 schedule

  • 4-8 May 2026 – BEXUS Critical Design Reviews (CDRs) and Soldering Course, ESA, ESTEC
  • Jul 2026 – BEXUS Integration Progress Reviews (IPRs) at student team sites
  • Aug/Sep 2026 – BEXUS Experiment Acceptance Reviews (EARs) at student team sites (ESA/SNSA) or ZARM-FAB Bremen (DLR)
  • 2-12 Oct 2026 – BEXUS Campaign (10 days), SSC, Esrange Space Center
  • Jan 2027 – Delivery of the final BEXUS Experiments reports

REXUS 37/38 schedule

  • 8-12 Jun 2026 – REXUS Critical Design Reviews (CDRs) and Soldering Course, DLR Oberpfaffenhofen
  • Aug 2026 – REXUS Integration Progress Reviews (IPRs) at student team sites
  • Nov 2026 – REXUS Experiment Acceptance Reviews (EARs) at student team sites
  • 7-11 Dec 2026 – Integration Week (ITW), ZARM-FAB Bremen
  • 18-22 Jan 2027 – Bench Test, DLR Oberpfaffenhofen
  • 1-13 Mar 2027 – REXUS Campaign (12 days), SSC, Esrange Space Center
  • Jun 2027 – Delivery of the final REXUS Experiments reports

Cycle 18:

  • 17 Jun 2026 – Call for Experiment Proposals
  • Sep 2025 – Letter of intent (DLR Only)
  • 8 Oct 2026, 12:00 CEST – Deadline for Experiment Proposals
  • 23-24 Nov 2026 – DLR Selection Workshop, DLR
  • 1-3 Dec 2026 – ESA/SNSA Selection Workshop, ESA/ESTEC
  • Dec 2026 – Cycle 18 selection announcement