Skip to content

Introduce feed-in limits to avoid unbound solution #1

@smartie2076

Description

@smartie2076

When the feed-in tariff is higher than the levelized generation costs of a (renewable) generation asset and the transformer station to the electrical grid is being optimized, the optimization problem can not be solved as the optimal solution would require an infinitive capacity/feed-in.
We need to cap this feed-in (eg. x times of total demand p.a.), to allow the solver to run-through. An message should then be displayed to the user, saying
"Please check the feed-in tariff and component costs. If both are correct, it might be a business plan to place a grid-feeding power plant inside your local electricity system."

Metadata

Metadata

Assignees

No one assigned

    Labels

    enhancementNew feature or requestinvalidThis doesn't seem right

    Type

    No type

    Projects

    No projects

    Milestone

    No milestone

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions