Is your feature request related to a problem or challenge? Please describe what you are trying to do.
The implementation for get_next_schedulable_task() is not efficient due to lack of classification of task stages and task status, especially when there's thousands of tasks to be scheduled. And it's also not easy to:
- stage-level priority-based scheduling
- stage-level retry
- speculative task scheduling
Describe the solution you'd like
To draw lessons from the Spark, it's better to divide the task scheduling into two levels' scheduling:
- to introduce QueryStageScheduler for scheduling stages
- to introduce StageManager for managing job stages and the state machine for each stage.
- to let TaskScheduler for fetching tasks from running stages in StageManager
An example sequential diagram is as follows: