@@ -207,6 +207,83 @@ Severity reflects plausible data loss, ownership corruption, permission/context
207207
| LIFE-GAP-037 | Medium-high | High | Singleton tool handlers share partial presentation state across calls/tasks, so interleaved paths can cause false or missed stabilization. | Interleave A:`x`, B:`y`, A:`x` or A:`x`, B:`x` through one handler's `lastSeenPartialPath`. | Per-call handler state keyed by task and tool-call identity. | Isolate partial state by `(taskId, toolCallId)` or handler instance; prove independent stabilization and cleanup after success, malformed finalization, rejection, cancellation, abandonment, and incomplete streams. |
208208
| LIFE-GAP-038 | High | High | Lossy tool-ID canonicalization can deduplicate persisted history without deduplicating execution, results, approvals, or pending-action replay. | Distinct raw IDs such as `call:a` and `call/a` both sanitize to `call_a`; history may retain one call while execution retains both. | One collision-resistant canonical call identity before indexing and persistence. | Reject or disambiguate collisions; prove a bijection among parsed call, durable tool use, approval, execution, result, pending action, and replay; test adversarial native/MCP IDs and restart between approval and settlement. |
209209

210+
## Portfolio remediation plan
211+
212+
The 38 IDs are not 38 independent projects. They group into eight programs with shared root causes and implementation surfaces. Estimates are engineering effort, not calendar commitments; they include implementation, deterministic tests, proportional model/refinement work, documentation, and stabilization.
213+
214+
| Cluster | Gap IDs | Root fix and likely ownership | Size / effort | Engineering risk | Objective portfolio evidence |
215+
| ------------------------------------------ | -------------------------------------- | ---------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------- | -------------------------------------------- | --------------------------------------------------------- | ------------------------------------------------------------------------------------------------------------------------------------ |
216+
| P1. Persisted ownership and generation | 001, 002, 012, 017, 020 | Disk-authoritative lifecycle ownership/generation and immutable store reads across history types, lifecycle reducers, `TaskHistoryStore`, provider delegation, and reconciliation. | XL, 15–25 engineer-days | High: persisted compatibility and cross-host races | Two-host stale-write tests, promoted invariants, restart/reconciliation evidence, backward-compatible optional data. |
217+
| P2. Durable operation and crash recovery | 004, 005, 006, 021, 023 | Operation intent/replay or explicit idempotent recovery for pair writes, delegation, completion messages, shutdown, and deletion. | XL, 20–35 days | Very high: failure ordering can create new corruption | Fault injection at every durable boundary, crash/restart convergence, no false success, recovery reachability. |
218+
| P3. Schema, path, and lifecycle vocabulary | 013, 018, 019 | Schema-derived status ownership, validated ordinary history reads, and one safe task-ID boundary across types, persistence, metadata, CLI, and import paths. | M, 5–9 days | Medium: malformed legacy data and downgrade behavior | Migration/quarantine fixtures, traversal tests, type/static ratchets. |
219+
| P4. Request, stream, and tool identity | 008, 010, 024, 025, 026, 030, 037, 038 | Request generation plus canonical call identity, then task/generation/call-scoped parser and partial-handler state. Owners include provider transforms, parser, `Task`, `BaseTool`, editing handlers, and tool-ID utilities. | XL, 18–30 days | High: provider compatibility and duplicate execution | Adversarial IDs/index-less streams, delayed/cancelled generation tests, cleanup/deadline checks, production-backed call-state model. |
220+
| P5. Tool-owned task state and queueing | 003, 007, 031, 035, 036 | Task-local context, durable child initialization, correlated approval identity, and claim/persist/ack queueing across tools, `Task`, provider/webview, message queue, and history schema. | XL, 16–27 days | High: cross-task contamination and persistence precedence | Omitted/explicit child controls, switch/restart E2E, two-approval schedules, queue failure retention, mode-permission tests. |
221+
| P6. Event and ingress contracts | 009, 011, 022, 027, 028, 029, 032, 033 | Classify barriers versus notifications; normalize lifecycle payloads and clear/resume semantics across Task, provider, public API, IPC, and webview. | L, 12–20 days | Medium-high: public compatibility and ordering | Exactly-once event tests, consumer inventory, cross-surface contract matrix, compatibility adapters where required. |
222+
| P7. Scheduler and fan-out decision | 014 | Enforce serial capacity, or implement live-parent fan-out across scheduler, registry, routing, rollback, orphan cleanup, webview scoping, and E2E. | Serial: M, 3–6 days. Fan-out: XL, 20–35 days | Serial low-medium; fan-out very high | Serial API/capacity ratchet, or production imports plus concurrent/failure E2E before fan-out reclassification. |
223+
| P8. Verification and traceability platform | 015, 016, 034 | Machine-readable model metadata/traceability and selected cross-model trace validation across checker scripts, package commands, CI, and architecture docs. | L, 7–12 days | Medium: vacuity and CI cost | CI validates IDs, symbols, tests, bounds, actions, landmarks, workflows, and executable mappings for cross-model claims. |
224+
225+
### Root fixes that close multiple gaps
226+
227+
- One persisted generation and disk-authoritative ownership design should close 001, 002, and 012; immutable reads and explicit reconciliation semantics address 017/020 around that owner.
228+
- One durable operation-intent/replay framework can support 004, 005, 006, 021, and 023, but each operation still needs its own legal recovery states and fault-injection matrix.
229+
- One request-generation/canonical-call identity established before parser indexing can support 008, 010, 024–026, 030, 037, and 038.
230+
- One correlated `(taskId, actionId, toolCallId)` approval protocol can close 036 and support 007/035; it does not itself make child state durable.
231+
- One typed lifecycle operation layer can normalize P6, but public compatibility requires separate adapters rather than a flag-day payload rewrite.
232+
233+
### Independent work that should not be collapsed
234+
235+
- Schema/path hardening (P3) is reviewable independently from transaction recovery (P2), despite shared persistence files.
236+
- Serial-versus-fan-out is a product decision and must not be hidden inside scheduler cleanup.
237+
- Completion consumer contracts (011) are not solved by safe EventEmitter listeners (009).
238+
- Durable child initialization (035) and approval correlation (036) need separate persistence and cancellation owners.
239+
- Verification platform work can proceed in parallel, but cannot promote another cluster before its production transition exists.
240+
241+
### Sequencing and critical path
242+
243+
1. **Foundation:** choose serial versus fan-out (serial recommended for current behavior), define lifecycle ownership/generation (P1), and define canonical request/tool identity (P4).
244+
2. **Integrity:** build durable operation recovery (P2) on P1. Run P3 in parallel once legacy-data policy is settled.
245+
3. **Task isolation:** implement P5 using P4 identity and P1/P2 persistence rules.
246+
4. **Surface convergence:** implement P6 after barrier/notification and generation semantics are known.
247+
5. **Mechanical assurance:** start P8 metadata early; add cross-model refinement as production owners land.
248+
249+
Critical path: **P7 decision → P1 ownership/generation → P2 recovery → P5 durable task state → P6 public contracts**. P3 and P8 metadata can run in parallel from the first tranche. P4 can run beside P1 after agreeing how task and request generations relate.
250+
251+
### Quick wins versus architectural programs
252+
253+
| Category | Scope | Effort | Notes |
254+
| ---------------------- | --------------------------------------------------------------------------------------------------------------------------------------------- | ---------------------- | --------------------------------------------------------------------------------- |
255+
| Quick wins | 013 shared status type; 025 listener cleanup; 029 projection naming/contracts; 034 checker metadata. | 1–4 days each | Separate PRs; reduce drift but do not close cross-host integrity. |
256+
| Medium projects | 019 path safety, 021 disposal drain, 022/033 ingress convergence, 024 parser cleanup, 026 hard deadline, 027/028 event ownership, serial 014. | 3–8 days each | Focused subsystem work with deterministic tests. |
257+
| Architectural programs | P1, P2, P4 identity/generation, P5 durable task state, P6 public contracts, or full fan-out. | 12–35 days per program | Require staged PRs, failure injection, compatibility plans, and model refinement. |
258+
259+
### Overall scale and parallel workstreams
260+
261+
With the recommended serial contract, shared infrastructure reduces the portfolio to approximately **85–145 engineer-days**. Full fan-out raises it to roughly **105–175 engineer-days** and increases critical-path risk. These are effort confidence bands, not delivery dates.
262+
263+
Four workstreams can proceed concurrently after foundation decisions:
264+
265+
1. persistence ownership/recovery (P1/P2);
266+
2. request/tool identity and streaming (P4);
267+
3. schema/path hardening and verification metadata (P3 plus P8 metadata);
268+
4. event/ingress compatibility design (P6 discovery, implementation after generation semantics).
269+
270+
### Recommended first tranche
271+
272+
1. Decide and enforce serial behavior for 014 unless fan-out is explicitly funded.
273+
2. Add deterministic failing tests for 001/002/012, then implement their shared ownership/generation primitive.
274+
3. Define canonical call identity and adversarial tests for 038/008; reuse it for 037 and 036.
275+
4. Land independent hardening for 013, 025, 029, and 034.
276+
5. Add P8 machine-readable mapping incrementally so closure PRs name symbols, witnesses, tests, bounds, and evidence class.
277+
278+
### Sizing assumptions and reconciliations
279+
280+
- Effort includes focused/full tests and relevant E2E, not only code edits.
281+
- Crash-consistency closure requires deterministic interruption and rollback fault injection; happy paths do not close P2.
282+
- Prefer lazy optional-field migrations. Existing lost data is unrecoverable; downgrade readers must ignore new fields safely.
283+
- High severity is reserved for demonstrated corruption, cross-task permission/state contamination, or execution/history divergence. Gap 035 remains Medium because its confirmed witness loses planning state; 036 and 038 remain High because they cross task/call ownership.
284+
- Gap 014 remains Medium while fan-out is disabled; risk rises if production concurrency is enabled prematurely.
285+
- Re-estimate after P1, P4, and P7 decisions because they define shared interfaces.
286+
210287
## Burn-down dependencies
211288

212289