Repository navigation
Description
Current status, September 22
Partial work has shipped in #397 (realtime service boundary), #396 (metadata), #444 (backup capture) and #472 (Docker evaluation); #486 extends the evaluation launcher. The production gates remain owned by #391, #392, #393 and #394, with catalog generation in #395. A dated source release can still ship with self-hosting explicitly marked Preview; it does not complete this epic.
Original requirements
Goal
Create one provider-neutral, upstream-maintained Orbit deployment kit that can be translated into Coolify, Dokploy, Easypanel, CapRover, Runtipi, CasaOS, Portainer, Railway, Zeabur, Sealos, Render, Helm, and managed-hosting catalog submissions.
This epic consolidates the distribution-specific acceptance criteria around the existing open-source readiness work. It does not weaken any P0 or P1 security/reliability gate in docs/open-source-readiness.md.
P0 release gate
- Portable production realtime topology without Vercel-only WebSocket behavior
- Versioned production web and realtime images
- Multi-architecture
amd64andarm64publishing to GHCR - Complete production
compose.yamlfor web, realtime, Postgres, Redis, object storage, and one-shot migrations - No committed default credentials
- Generated or required application, database, Redis, and object-storage secrets
- Safe first-owner bootstrap that cannot be claimed by an arbitrary first visitor
- Self-contained first-login path without requiring Resend or third-party OAuth
- Idempotent, locked production migration job
- Minimal liveness and readiness checks
- Documented persistent-data contract
- Automated Postgres and object-storage backup/restore test
- Stable version/update contract with immutable image digests and upgrade notes
- Reverse-proxy tests for nginx, Caddy, and Traefik
- Clean-install, restart-persistence, and previous-release upgrade test in CI
P1 distribution assets
- SBOM and provenance/signature for each image
- Vulnerability scan attached to releases
- Minimum and recommended CPU, RAM, and storage
- Provider-neutral install, upgrade, backup, restore, and troubleshooting docs
- Stable support and security-reporting URLs
- SVG logo plus 256, 400, and 512 px PNG variants
- Three to five current screenshots that work in light and dark catalog surfaces
- Canonical short and long descriptions
First submission wave after P0
- Big Bear Universal Apps
- Dokploy Templates
- Easypanel Templates
- CapRover One-Click Apps
- Runtipi Official App Store
- CasaOS / ZimaOS App Store
- Portainer Templates
- Railway Template Marketplace
- Zeabur Template Marketplace
- Sealos App Store
- DeployStack
- Render Blueprint
- Coolify deploy-from-repository documentation
Hard gates
- Coolify official catalog: submit only after satisfying its then-current upstream-star threshold and all service contribution requirements.
- Awesome-Selfhosted: submit only after satisfying its release-age and provider-neutrality rules.
Required clean-install evidence for every catalog PR
- Deploy from a blank account or host.
- Complete first-owner setup.
- Create an issue and doc.
- Verify realtime synchronization in two browser sessions.
- Upload and read an attachment.
- Restart every application container and verify persistence.
- Upgrade from the preceding supported release.
- Restore a database and object-storage backup.
- Record platform version, image digests, logs, and screenshots.
Architecture rule
Maintain one canonical deployment definition under the Orbit repository and generate or derive platform-specific manifests wherever practical. Do not allow dozens of independently edited templates to drift.
Activity
imshashank commentedon Sep 3, 2026
Implementation breakdown — 2026-09-04
The first three focused deployment workstreams are now specified:
Each issue includes current code boundaries, likely files, security invariants, and end-to-end acceptance tests. They are implementation issues only; no pull requests have been created or merged for this work.
Remaining focused work before the first catalog wave:
imshashank commentedon Sep 3, 2026
Deployment-kit workstream map
The production distribution work is now decomposed into five focused issues:
Recommended dependency order:
Some work can proceed in parallel, especially schema/copy/asset inventory in #395, but no one-click catalog output should claim production readiness before #391–#394 pass their end-to-end gates.