Description
Problem
Several open M3/M4 umbrella issues (#25, #26, #30, #31, #32,
#33, #34) had significant progress in v0.2.0 but no comment
yet captures that progress. The issues read as if no work
has happened, which masks the actual state.
Scope
For each of these issues, add a comment summarizing what
v0.2.0 shipped against the acceptance criteria and what
remains:
- M3-04: Link
ElemTableids to partition record offsets #25 (M3-04 ElemTable->partition link) — DONE per RE-14.7
IdOffsetIndex (M10-03: Add issue form for corpus submissions #62 in CHANGELOG). Likely closable. - M3-05: Implement typed partition decoders for the MVP classes #26 (M3-05 typed partition decoders) — Level/Wall/Floor/
Door/Material/Category/FamilyInstance shipped at varying
recall. WallType/FloorType + Window separately + Room names
still pending. Keep open. - M4-02: Recover wall geometry #30 (M4-02 wall geometry) — Walls emit at 82% recall but
with placeholder rectangular geometry. Real geometry pending
(RE-15-01 + RE-15-08 + 2024 ArcWall envelope per M3-02: Reverse-engineer Revit 2024 ArcWall records #23). - M4-03: Recover floor and slab geometry #31 (M4-03 slab geometry) — Slabs at 76% recall, placeholder
extrusion. Real boundaries via RE-15-07. - M4-04: Recover doors and windows with host relationships #32 (M4-04 doors+windows host) — Doors at 85% recall, no
openings yet. Windows not started. RE-15-02/09/11 cover. - M4-05: Recover levels and storey assignment #33 (M4-05 levels+storey) — Storeys 15/15 with real
elevations, per-element routing DONE. Names placeholder
(RE-15-06). - M4-06: Recover materials and compound assemblies #34 (M4-06 materials+compounds) — Materials 10/10 emit,
names placeholder, no compound-layer/usage wiring (RE-15-06- RE-15-08).
Acceptance criteria
- All 7 listed issues have a v0.2.0-progress comment.
- M3-04: Link
ElemTableids to partition record offsets #25 closed if M3-04 acceptance criteria are met by RE-14.7. - Each comment links to the corresponding new RE-15-NN / CLASS-NN
follow-up issue created in this batch.
Metadata
Metadata
Assignees
Labels
priority:P2Important quality, usability, or hardening work.type:project-managementRepository planning, triage, or contribution workflow.
Activity
DrunkOnJava commentedon Aug 28, 2026
Triage probe: verifying write access for OPS-03 progress comments against
main@21aa0e0.DrunkOnJava commentedon Aug 28, 2026
OPS-03 complete (2026-08-28)
Commented v0.2.0+ /
main@21aa0e0progress on the listed umbrellas:IdOffsetIndex/ElementId→PartitionRecordRefonmainbuilding_storeys; fixtureknown_gapAlso closed fully-met adjacent issues found during this triage: #19, #21, #29, #36, #39, #45.
Full write-up: agent artifact
issue_triage_report.md(also summarized for maintainers in that file).Closing this OPS issue as completed.
DrunkOnJava commentedon Aug 28, 2026
Milestone note (2026-08-28 triage)
Milestone
0.2.0: audit-clean alphais effectively complete: 0 open / 19 closed, but the milestone itself is stillstate: open.Available automation tokens can comment/close issues but cannot PATCH milestones (403). Please close milestone #1 (
0.2.0: audit-clean alpha) manually in GitHub UI when convenient.Related triage closed outside that milestone during the same pass: #19 #21 #29 #36 #39 #45 #99.