10.x takes additions for six months after v11.0.0, not only until it #178
The release rules contradict each other. CONTRIBUTING.md#branches-and-releases says additions ship as 10.x minors until v11.0.0, and 10.x takes fixes only after it. #149 says the closed unions ship on 10.x as a minor after .NET 11 GA, which is when v11.0.0 ships, so under the written rule they can't. The rule also leaves the LTS line a window of a few weeks for additions, because v11.0.0 follows .NET 11 GA (November 2026).
Decision (maintainer, 2026-10-18)
10.x takes additions for six months after v11.0.0, then fixes only. An addition still reaches main first and is cherry-picked (-x) into a PR against release/10.x, so the LTS line never carries something the current line lacks. The cut-off is a date written into CONTRIBUTING when v11.0.0 is tagged (tag date + 6 months).
Change
CONTRIBUTING.md: the "Additions" bullet and the paragraph after it.