Every year from about the middle of September, the question changes. People stop asking what a kitchen costs and start asking whether it can be finished in time.
It is a fair question and it deserves a straight answer rather than an optimistic one. So here is roughly how a kitchen actually runs, where the time really goes, and what the honest cut-off looks like if you want to be cooking in it before the end of the year.
The answer depends almost entirely on one decision
Not the countertop. The cabinets.
Countertop fabrication runs on a fairly predictable schedule. Cabinets are where the range is enormous, and the choice you make there sets the length of the whole project:
- Flat-pack (RTA) cabinets — about a week, or sooner if what you want is already in stock
- Semi-custom — around four to six weeks
- Full-custom — six to eight weeks
That is the difference between a kitchen that could start this week and one that starts after the new year. Everything else is comparatively minor.
Why countertops come second, and why that is not negotiable
We cannot template your countertops until the cabinets are physically in place and level. Not when they are ordered, not when they are delivered — in place.
A template is a record of the room as it actually exists, not as it was drawn. Walls are rarely straight, floors are rarely level, and the gap between a cabinet run and the wall behind it is almost never the gap on the plan. A countertop cut from a drawing rather than a template will fit approximately, and approximately is visible for the lifetime of the kitchen.
So the sequence is fixed: cabinets ordered, cabinets delivered, cabinets installed and levelled, then template, then fabrication, then install. Trying to compress that by templating early produces a countertop that does not sit right, and you will see it every day.
After templating, fabrication and installation follow on a schedule we will give you a date for.
Where the delays actually come from
Very few projects run late because a trade was slow. They run late because of decisions.
Choosing the slab. People take longer over this than they expect, and they are right to — it is the surface they will look at every morning for fifteen years. But the clock does not start until it is chosen.
Changing a colour after the order has gone in. On a flat-pack line this might cost days. On a custom line it can reset the entire manufacturing window. The order is the point of no return.
What is found behind the old kitchen. Plumbing that was not where anyone thought. Electrical that will not pass as it stands. A floor that drops an inch across the run. None of it is anyone’s fault and all of it takes time to put right.
The projects that finish on schedule are almost always the ones where decisions were made early and then left alone.
Working backwards from the holidays
If the goal is a finished kitchen by the third week of December, here is roughly where you need to be:
Full-custom cabinets — the order needed to be in by the middle of October. Six to eight weeks from order to cabinets on site, then installation, then the countertop sequence after that. If you are reading this later than that and you want full-custom, the honest answer is the new year.
Semi-custom — ordering in the next week or two is tight but workable. Four to six weeks from order takes you to early December, which leaves enough room for installation and countertops if nothing goes wrong. It leaves very little room for anything that does.
Flat-pack — comfortably achievable. If the cabinets you want are in stock they can be with you inside a week, which means the only real variable left is scheduling the trades and the countertop fabrication.
If you have left it late
You have not necessarily lost. You have narrowed your options, which is a different thing.
The flat-pack route is genuinely good — solid-wood plywood boxes with full-opening drawers and soft-close hinges, the same construction as the lines that take weeks longer. What you give up is breadth of colour and door style, not quality. For a lot of people that is an easy trade when the alternative is waiting until the new year.
It is also the route we have built our Early Black Friday bundles around, for exactly this reason. Countertops, cabinets and an undermount sink are quoted together as one package rather than three separate jobs, at six fixed prices starting from $2,675 plus tax for a 10′×10′ kitchen. One order, one install date to plan around, and the lead times above are the short ones. The offer runs until 27 November.
Whichever way you go, choose your countertop material now rather than later. Picking the slab is the step people underestimate, and doing it early buys back more time than almost anything else.
What we would tell you on the phone
If you call and ask whether we can do it, the first question back will be which cabinets, and the second will be whether you have measurements. From those two answers we can usually tell you within a minute whether December is realistic.
We would rather say it is not than take an order we cannot deliver. A kitchen finished in January that was promised for Christmas is a bad experience however good the kitchen turns out.
Book a free consultation and we will give you a real date rather than a hopeful one. If you are still weighing up cabinet lines, this breakdown of RTA, semi-custom and full-custom covers the trade-offs, and you can see the materials and styles we work with first.